Comparing Quotes Properly: Unit Price Versus Landed Cost

2026-10-27  Period:Unlimited - Unlimited 35

Two quotations for the same product are rarely the same product, and almost never the same deal. The unit price on the page is the least reliable number in a sourcing decision, because it excludes everything that varies between suppliers: specification, packaging, freight basis, payment terms, and what happens when something goes wrong. This guide sets out how to compare on landed cost without needing a spreadsheet model nobody will maintain.

Why unit price misleads

A lower unit price usually reflects a difference somewhere in the specification, whether or not the supplier mentions it. Common sources of a deceptively low price:

The countermeasure is simple and unglamorous: normalise every quote against an identical written specification before comparing any number.

Build the landed cost line by line

ComponentWhat to includeWhere it hides
ProductUnit price at your real order quantity, per SKUQuotes priced at a breakpoint you will not reach
PackagingFilm, carton, labels, plates or cylinders for custom printQuoted separately or "to be confirmed"
ToolingOne-off plate, cylinder or mould cost, amortised over your expected volumeOmitted from the comparison entirely
Inland and export handlingTrucking, export clearance, port chargesIncluded in one quote and excluded from another under the same Incoterm label
Main freightOcean or air, per container or per kilogram chargeableEstimates presented as facts; verify against a forwarder
InsuranceCover level and costAssumed rather than priced
Duty and taxesBased on the classification your broker confirmsIgnored in CIF quotes because it is not the seller's cost
Destination chargesPort, clearance, delivery, and any demurrage riskAlmost always excluded from the quote
Quality costInspection, testing, and expected defect rateInvisible until the first claim
Working capitalEffect of payment terms on cash tied upNever in the quote, always in the cost

You do not need precision on every line. You need every line to appear, so that the comparison is between comparable things.

Payment terms are part of the price

A 30% deposit with 70% before shipment and a 100% letter of credit are different financial products, and the difference is a real cost. If one supplier requires full payment at production and another accepts payment against documents, the second is cheaper than the headline numbers suggest even at a higher unit price. Quantify it roughly: the cost of the credit, the length of time cash is committed, and the risk carried in each structure. For a first order with a new supplier, the risk dimension usually outweighs the financing dimension.

Quantity breakpoints and the honesty of your forecast

Quotes are usually stepped by quantity. The cheapest column is often a volume you will not reach in the first year, and committing to it to capture a lower price can leave you with inventory you cannot sell. Compare at three quantities: your first order, your expected annual volume, and your optimistic case. Where a supplier's price curve is steep, ask what drives it — material purchasing, line changeover, or packaging plates — because the answer tells you which volume threshold actually matters.

Total cost of a bad batch

The cost that never appears in a quotation is the failure cost. Estimate it before you need it:

A supplier who is 8% cheaper with no inspection plan and no documented method is not cheaper. The specification and inspection basis covered in Common Defects and Prevention is what converts that risk into a measurable line.

A short comparison procedure

For the shipping components of landed cost, see Incoterms and Shipping. For the specification side, start from Sourcing Checklist and Absorbent Core Basics.